Sizewell C – Wrong Project, Wrong Time, Wrong Place.

Stop Sizewell C statement on Sizewell C’s Final Investment Decision, 22 July 2025.

“This much-delayed Final Investment Decision has only crawled over the line thanks to guarantees that the public purse, not private investors, will carry the can for the inevitable cost overruns. Even so, UK households will soon be hit with a new Sizewell C construction tax on their energy bills. It is astounding that it is only now, as contracts are being signed, that the government has confessed that Sizewell C’s cost has almost doubled to an eye watering £38 billion – a figure that will only go up. Given that Ministers claimed not to recognise the cost was close to £40 billion is there any wonder there is so little trust in this project?”

WHAT YOU CAN DO…

StopSizewellC on X (Twitter)

Rolls Royce criticised for outsourcing components of its Small Modular Reactors to South Korea? With "multi-billion euro" contracts going to #Framatome, #SizewellC is not exactly buying British either...
#StopSizewellC

"[#HinkleyC] workers are unhappy with a proposed change to shift patterns that will see them on duty for 10 days in a row every fortnight... [also] claims regarding the safety of an area used to clock on/off tho EDF firmly denies these"
#StopSizewellC

Can definitely see this happening here - indeed it already is with #SizewellC taking over Pontins Pakefield and plans for Darsham High Lodge...
#StopSizewellC

"On average #nuclear projects worldwide end up with construction cost overruns of about 100% ... every new project will ultimately face the same test as every other technology: how fast can it deliver, at what cost, and at what risk?"
#StopSizewellC

Load More

StopSizewellC on Facebook

Stop Sizewell C
Stop Sizewell C1 day ago
Rolls Royce criticised for outsourcing components of its Small Modular Reactors to South Korea? With "multi-billion euro" contracts going to #Framatome, #SizewellC is not exactly buying British either...
#StopSizewellC
Stop Sizewell C
Stop Sizewell C1 day ago
"The [#HinkleyC] workers are believed to be unhappy with a proposed change to shift patterns being introduced in July that will see them on duty for 10 days in a row every fortnight. CN understands there have also been claims made regarding the safety of an area used to clock on and off shift, although EDF firmly denies these claims."
#StopSizewellC
Stop Sizewell C
Stop Sizewell C4 days ago
Can definitely see this happening here - indeed it already is with #SizewellC taking over Pontins Pakefield and plans for Darsham High Lodge...
#StopSizewellC
Stop Sizewell C
Stop Sizewell C6 days ago
"On average #nuclear projects worldwide end up with construction cost overruns of about 100% ... every new project will ultimately face the same test as every other technology: how fast can it deliver, at what cost, and at what risk?"
#StopSizewellC
Stop Sizewell C
Stop Sizewell C1 week ago
If #SizewellC was genuinely delayed by judicial reviews, why did the National Audit Office, who would have spoken at length to the Department for Energy Security and Net Zero and #SizewellC during their enquiries, not say so? If the Chancellor is going to persist in using such offensive ["blockers"] language, she really ought to get her facts right."
#StopSizewellC

NB The NAO said a Final Investment Decision was made "4.5 years after negotiations started and at least 28 months later than originally planned. The project was delayed several times, including by the 2024 General Election; responding to feedback from potential investors and the government’s internal assurance processes; and longer than expected negotiations with EDF and the other investors."

Stop Sizewell C
Stop Sizewell C1 week ago
"£1bn will be added to bills by a #nuclear levy supporting construction of #SizewellC..led by EDF...For decades these power stations will pump electricity into homes while also sucking cash from households and sending it to investors abroad"
#StopSizewellC